SITE PREPARATION (LEVELING)
The
first step in the construction is site preparation. Site preparation consists
of clearing away the trees from construction site, and doing whatever rough
grading that is necessary in the installation of the footings and foundation.
Clearing involves the removal of trees, roots, and other vegetation from the
site. This can done using manual labor as well as excavators. The debris
removed using a dozer.
After
clearing the site, the undulations in the terrain have to be roughly leveled. Dozers
used to level the plot.
SITE MARKING
Before
the excavation of soil is started, the layout of the structure has to be marked
on the ground. This process is called Site marking. This is a very important
step, because here we begin the construction part. The slackness made in layout
causes extensively damage to the work and heavy loss to the owner. If a
building is constructed with an inaccurate marking, it can even affect the
stability and aesthetics of the building. The center line, base line, etc. are
fixed prior to the marking. Using pegs and ropes the layout for excavation is
clearly marked to project the plan on the ground.
EXCAVATION
Excavation is the
removal of soil from the surface to form a trench of required depth in which
the foundation is built. Usually a backhoe or a digger (JCB) is used for this
purpose. For smaller works manual labor is sufficient. The excavated soil can
either be transported to some other place, or if back-filling is required, is
dumped near to the trench or sideways.
COMPACTION
Compaction
of back filled material is one of the most important aspects in the
construction of structural buildings. Benefits of soil compaction are reducing
its compressibility and increase its strength. By doing proper compaction of
back filled soil, we can avoid lot of problems will arise later such as crack
formation in ground floor
In our site expedite the process,
soil was just filled the required level and compact with vibration plate then
filled the 100 mm above the required level and compacted till the required
level. Level should be maintained from offline of thread. Spray water to soil
during the compaction to increase the compact ability.
Benefit
of Compaction
- Increase Load-bearing Capacity
- Prevents Soil Settlement (Better Stability)
- Reduce Water Seepage
- Reduces Shrinkage and others
What is used to compaction?
To compact soil, tamping rammer is used.
How
to check whether it is properly compacted?
To check whether it
is compacted. Several test are carried out. One method is sand cone test.