After winning a
contract, client has handover the land to the contractor to start the
construction work. But the contractor can’t start the work just after he gets
the site premises. The contractor should plan the arrangement of site. Without
doing that, he can’t do his job properly. If the contractor starts the
construction work without doing site mobilization, he will definitely be in
trouble. So every contractor should mobilized his site according to the job he
has assigned. That’s why in the tender documents and in the BOQ, that is
clearly mentioned. The amount of money reserved for the mobilization is depends
on the project. And also the duration for the mobilization is also clearly
showed in the “Construction Master Schedule, (CMS)”. After providing the
essential facilities for the staff and Labour contractor can start the
construction work and while doing the work he can mobilize the other
requirements of the site
There
are few items have to provide at the beginning of a project, by the contractor.
Those are;
- Accesses roads
- Water
- Electricity
- Communication
- Site office
- Labour Accommodation
- Stores
- Bar bending yard
- Toilets
In
any construction project, the most important material should be the water.
Because we need water for many works carried out at the site. So at the
beginning of project, contractor should find the water resources for the humans
and for the construction work. Other important fact is Electricity. This is the
main power source for the site work. This is very important, because there are
so many equipment used at the site running by electricity. And also for the
lighting at the night, electricity is needed. So at the first stage of
mobilization, the contractor should provide these to resources.
In
any construction project, there is a staff to do the day-to-day work at the
site. They are from the contractor’s party and consultant party. In
multimillion projects, lots of people have involved to the construction work.
They should be the project manager, construction manager, site engineer,
quantity surveyor, or the consultant. So contractor must provide the office to
them for get the proper output from them.
Toilets & Showers
When doing a
construction project, lots of people are involved to do the work at site. They
should be the staff, direct labours or indirect labours and many more. To all
of them, contractor must provide the enough sanitary facilities.
Labour Accommodation
The
contractor should consider about the Labour accommodation. Because most of them
are in very far away to the site. So it is difficult to travel daily. Sometimes
they have to work at night, due to mass construction. (E.g.: slab concreting).
So to gain maximum output as well as to have good management it is necessary to
place the Labour accommodation.
It
should be in the site or near the site. In our site we prepared a temporary
huts for accommodating for labours.