INTRODUCTION
Form-work
is a temporary structure. It is a mould or die used to support and shape the
concrete until it attains sufficient to carry its own weight. The form-work
holds the concrete until it hardens to required shape and size. Once the
concrete develops adequate strength, the forms are removed.
- Form-work constitutes 30% of the cost and 60% of the time in concrete construction
- Quality of concrete finish and soundness of concrete depends very much on the form work system.
- Desired shape of concrete is not possible if form-work not done properly.
- Form-work should be properly designed, fabricated and erected to receive concrete.
- Accidents happen because of the faulty form-work and scaffolding or staging.
2 REQUIREMENTS OF FORM-WORK
There
are essential requirements for form-work. Any good form-work should satisfy all
of the following requirements.
Containment
Form-work
must be capable of shaping and supporting the fresh concrete until it becomes
hard.
Strength
Form-work
must be strong enough to withstand the dead weight of fresh concrete placed on
it. Also form-work should be strong enough to bear the imposed loads after
concrete placing.
Resistance to Leakage
All
joint in the form face should be either close fittings or covered with some
sheet material to make these grout tight. Grout leakage can lead two weak
concrete. It can cause honeycombing of the surface & may produce projecting
fins (snobs), which later have to be removed and touched up.
Accuracy
Form-work
must be accurately set out so that the resulting concreting elements is in the
right place and is of the correct shape and dimension. The degree of accuracy
concerned will be consistent with the item being cast.
Easy of Handling
Form
panels and units should be made so that they can be easily handled by hand or
mechanical means. In addition to all form work must also be designed and
constructed to include facilities for adjustment, leveling, erecting and
striking without damage to the formwork or concrete.
Form-work
must be capable of gradual and easily remove.
MATERIAL USED FOR FORM WORK
Plywood
This
is by far the most common material used for the facing panel. It is easily cut
to shape on site, and if handled and stored carefully. It is commonly used 8’×4’
sheet size. Thickness is 15mm. it is used for slab form-work, column boxes,
staircase form-work and beams etc. This 15 mm thick board can be used for 6
times. Applying mold oil, can increase usable of plywood board as well as the
quality of structure.
Advantages
of Using Plywood Sheets.
- Good surface finish can be obtained.
- Plywood form-work is economical because this can be used repeatedly although the cost of plywood is higher than class II timber planks.
- Since the plywood sheet covers large area, the time taken to construct the entire shuttering is less.
- It can be easily sawn to the required shape.
Disadvantage
of Using Plywood Sheets
- Even after removing the shuttering, adhered plywood particles can be seen on the surface when normal plywood used.
- Peeling of layers with the time.
- Due to the slenderness of the sheet large numbers of strengthening cleats are required, otherwise form-work gets deflected
Timber
This
is the most common material used for bracing members to the form face. Usually
use 2×2, 3×5 timbers for form-work.
GI pipes
It
was used to tighten the form work. This is a 50mm diameter bar.
Ties
Form-work
to vertical members such as walls normally requires ties to resist the pressure
of the concrete. These ties connect the outer framing member of one panel with
those of the opposite side of the walls so.
U Jack
This
used to support the columns and beams.
Power saw
This
used to cut the plywood as well as timbers.
Plumb-bob
This
used to check the verticality of columns.
Other
Material used for form-work
- Concrete nails & wire nails.
- Thread bars
- Clamp (Fix, Free)
- Adjustable steel props
- Chain
- Mould oil
CLEANING AND TREATING OF FORM WORK
All
rubbish, particularly chippings, shavings and saw dust, was removed from the
interior of the forms before the concrete is placed. The form work in contact
with the concrete was cleaned and thoroughly wetted or treated with an approved
composition (mold oil such as grease mixed with diesel) to prevent adhesion
between form work and concrete.
Before
concrete poured, the form-work is carefully examined to ensure the followings.
- Removal of all dirt, shavings, sawdust and other refuse by brushing and washing.
- The correct location of tie bars bracing and spacers, and especially connections of bracing.
- All panels are well sheeted and all supporters are well tightened.
- Whether cover blocks are properly placed.
- Whether column is checked for verticality.
FORM WORK FOR COLUMNS
Column box is done by using plywood
boards. To avoid plywood
joints, it is normal practice to cut the sheets length wise in widths to match
the column faces. The corners of the form are usually formed to have a 45
degree.
In our site most of them were
rectangular shape. In the case of the rectangular column, the form-work consists
of four shutters or panels made out of plywood board nailed securely to timber
planks
- 8’×4’ 15 mm thick Plywood board
- 2×2 timber
- 50 mm diameter GI pipes
- Corn tie
- U jack
- Plumb-bob
- Speed level to check off-set
First,
the surface was roughened for the purpose of well bonding with later concrete.
Then the four shutters were fixed together and GI pipes were hung with the
nails fixed to the plywood sheet using binding wires in each side vertically.
Then the horizontal pipes also fixed to the board by using the Form ties. The
adjustable jacks were fixed between the horizontal GI pipes and to a fixed
position of the floor. The cover blocks were also tightened to the reinforcement
at the top.
Placing the column and check verticality
To
place the form-work in right place, first should have to fix the kickers to the
top of slab surface considering the offset line which drawn by quantity surveyor.
After
constructing the form-work for columns it is necessary to check for correct
verticality before concreting.
For
small scale form-works a simple center plumb can be used to check the verticality.
Two
center plumbs and a steel tape is required for this process. Center plumbs were
hanged at two positions in the same plane with a known distance (i.e. 200 mm)
measured from the inner surface of the plywood sheet. The distance from the
plywood sheet to the thread of the center plumb is measured using the steel
tape at both top and the bottom of the form work.
Calculations
for a plywood form-work is as follows.
Offset
distance from the column edge
= 200 mm
Plywood
thickness = 15 mm
Distance
between the plywood and the plumb (X) = 200-15
X = 185 mm
If
the verticality of the column is accurate the distance between the plywood and
the center plumb thread should be 185 mm everywhere. Jack supports or locking
systems of the form-work can be adjusted to obtain the correct verticality in
case of a mismatch.
FORM WORK IN BEAMS AND SLAB
Ina
typical reinforced concrete building frame, the slab are the primary load
carrying element. They are transfer their load to secondary element such as
walls or beams.
Beams
can be grouped in two categories. When located in the interior of the structure
are usually T beams and when on the perimeter are L beams.
DESIGN AND CONSTRUCTION OF BEAMS
- Beam form-work consist of open through section and because it is not closed at the top. It needed more support to maintain the soffit and also provide lateral support to the sides.
- Beam soffit must be thickened timber (supported by 2×2 timber)
- Beam side 15 mm plywood with supported by braces.
- Beep beams (over 600 mm) should have wales and ties.
- Adjustable jacks must be placed under the beam bottom. (Distance between each supports approximately 1’6” or 2’)
SLAB
Form-work
for slabs consist of sheathing made of plywood, which rest on joists a joists
are supported by stringers and stringers are supported by on shores (U jacks
and scaffold) which carry the weight of entire system. Figure x shows a typical
slab form with its components.
Steps which carried out for constructing slab
form-work
- Place the beam bottoms and elevate to offset line using adjustable jacks which supported by beam bottom.
- Fix the beam sideboards.
- Place 2 set of scaffolds (for one height slab) to support the soffit.
- Place U jacks in four side of each scaffolds.
- Adjust that U jacks up to stringer bottom level.
Calculate
U jack level
Soffit
height = 2388 mm
Stringer
height = 27 mm
Height
of joist (GI pipe) = 50 mm
Thickness
of plywood = 15 mm
Reduce
height to string bottom level = 2296 mm
(Note: Soffit height measured by 1000 mm level
from F.F.L)
- After adjust 2 U jacks of sides that near to beams, then using thread other all U jacks can be adjustable
- Then place the 3×5 timber (stringer) on top of the U jack.
- After that place GI pipes in 1’ intervals.
Before
laying the plywood, should have to check followings:
- Stringers are positioned and set in line and adjusted to the correct level
- All stringers are plumb.
- Stringers joints are supported.
- Stringers are seated centrally on U head.
- Scaffold bracing are properly fixed.
- All supports are horizontally and diagonally braced.
- Then lay the 15 mm thick plywood on top of the GI pipe and place the side boards in beams.
When
sheeting,
- Edges are properly sealed (It will prevent swelling).
- Stick surface tape to joints if necessary.
- Check that joints are sealed, level and tight.
- After laying all the plywood boards, mold oil should be applied.
- Now is ready to do the reinforcement.
STOP BOARD CONSTRUCTION FOR SLABS AND BEAMS
FORM-WORK IN STAIRCASE
Stair form-work must
support the weight of concrete. The weight of the throat of the stair and the
steps will have to be supported. Because of the slope of the stair, some of the
force is transmitted sideways. All form-work must be well tied together to
prevent sideways movement.
WALL FORM-WORK
Wall form-work is a
simpler than for other concrete units as the actual forces against it are less,
most of the load being carried vertically downwards. The panels at both sides
are held in position by ties. Ties are also used as
spacer, arranging wall thickness. Wall support systems are usually sloping props
at satisfactory intervals.
REMOVAL OF FORM-WORK
Time of form-work removal depends on the
following factors.
- Type of cement
- Whether it is Ordinary Portland Cement (OPC)
- Ration of concrete mix
- Rich ration concrete gain strength earlier as compared to weak ratio of concrete.
- Weather condition
- Hydration process acceleration is hot weather condition as compared to cold and humid weather conditions
Form-work removal period
Column
formwork - 24hrs
Soffit
formwork of slab - 4 days
Soffit
formwork of beams - 10 days
Props
of slab - 10
days
Props
to beam - 14 days
Get one of the best gi pipe from one of the best gi pipe dealers.
ReplyDeleteAt this era the demand are increasing and JRS Pipes and tubes who also known as a gi pipe dealers.
ReplyDelete